Successful electrolysis test



Due date:
12.10.2024

From 7 to 12 October 2024, a five-day continuous operation test was carried out at demonstration plant with the aim of producing at least 132 kg of high-purity manganese metal (HPEMM). The electrolysis module of the demonstration plant worked without any interruption for 120 hours. In the end, we produced 172 kg HPEMM.